East Lothian Council

Tranent Care Facility Project

Published Tuesday 3rd April 12

Contractor to start ground stabilisation work next week.

Tranent Care Facility

Site preparation work has started for the new Council 60 bed residential home and day care facility in Tranent.

Programme Update

Ground Stabilisation Work

  • The site set-up will start on Wednesday 4 April.
  • Drilling and underground grouting will start from Tuesday 10 April.
  • Work will last for 6 weeks.
  • There will be some noise from drilling, but this is not expected to be severe.
  • There could be some dust, particularly if the weather is dry.
  • The work is necessary in preparation for the new 60 bed care facility.
  • Building which is expected to start in September.
  • Please be patient during this essential work.

Access for Contractors Vehicles

  • Delivery lorries will arrive from Sanderson’s Wynd via School Lane.
  • There will be no deliveries between  8.15 - 9.15am, nor 2.30 – 3.45pm.
  • Please take extra care if you need to use School Lane
    or when visiting the Local Area Office.

Contact Details

If you have any issues, please contact the site engineer on 07834 800 543
in the site office  or Customer Services in the Tranent Area Office.

Development Site

Tranent Care Facility Development Site

 

Tranent Care Facility – Proposed Site Layout

Tranent Care Facility Proposed Site Layout

More articles in the news archive.

Get this feed East Lothian Council news feed | About RSS.

East Lothian Council, John Muir House Brewery Park Haddington East Lothian EH41 3HA.