You must apply for your Road Construction Consent (RCC) at least three months prior to the proposed commencement of construction.
There is a charge of £525 per application, plus £37 per metre for the first 100 metres of road then £21 per metre for each subsequent metre, and £6 for each metre of path.
To apply for Road Construction Consent please email transportplanning@eastlothian.gov.uk with the location plan. We will then respond with payment options, and can discuss the best way of submitting documents for assessment.
In order to determine an application we require the following documents as a minimum:
East Lothian Council checksheets
You will find it helpful to complete the checksheets below before making a submission. These identify what we we will be looking for as we assess the Road Construction Consent.
Neighbour Notifications
The developer is required to notify any person who owns land which fronts, abuts or is comprehended in the new roads, or which lies within 50m of the road for which Road Construction Consent is being sought. You can use Form CC3 to issue the notifications.
Scottish Water Approval
Evidence of Scottish Water's Technical Approval will be required, and this must reference current revisions of the drawings.
Email flooding@eastlothian.gov.uk with any queries relating to drainage and flooding.
Drainage Assessment
Evidence that the Drainage Assessment, including a Surface Water Management Plan has been submitted to and approved by the Statutory Authorities.
Any questions about the Drainage Assessment requirements should be directed to flooding@eastlothian.gov.uk.
DNO comments on EV infrastructure
We require confirmation from the DNO (electrical Distribution Network Operator, currently SPEN for our area) regarding the suitability of the grid connection for vehicle chargers.
Questions should be directed to evcharging@eastlothian.gov.uk.
Structures Technical Approval
Where the submission includes structures associated with the road network (e.g. retaining walls, culverts or bridges) the application will be subject to Technical Approval Procedures as outlined in CG 300 of the Design Manual for Roads & Bridges, and Technical Approval must be sought before the application for an RCC. If the need for an additional or amended structure arises after the granting of Road Construction Consent, the developer should seek the approval of the Council’s Roads Authority before starting construction of it.
Any questions about Structures Technical Approval should be directed to bridges@eastlothian.gov.uk.
Lighting Calculations
Please note that you will be expected to ensure that lighting on existing roads is suitable for any new accesses. Email stlighting@eastlothian.gov.uk with any queries relating to lighting.
Mineral Working Report
In areas that are known to have been in-filled or have a history of mineral workings, we may require a mineral report together with supporting information on ground stability.
Note: These webpages are for reference by developers of housing and employment sites in East Lothian. They provide guidance on transport infrastructure against which Planning Applications will be assessed and evaluated, and set out East Lothian Council's procedures regarding the construction and adoption of new roads in accordance with current legislation. These pages supersede all previous versions of our Standards for Development Roads document.