Part 1: Process and authority

1.4 Apply for Road Construction Consent

1.4.1 Apply for Road Construction Consent

You must apply for your Road Construction Consent (RCC) at least three months prior to the proposed commencement of construction. 

There is a charge of £525 per application, plus £37 per metre for the first 100 metres of road then £21 per metre for each subsequent metre, and £6 for each metre of path.

To apply for Road Construction Consent please email transportplanning@eastlothian.gov.uk with the location plan. We will then respond with payment options, and can discuss the best way of submitting documents for assessment.

In order to determine an application we require the following documents as a minimum:

  • forms CC1, CC2 and CC3
  • location plan
  • general arrangement plan (in the context of any surrounding development phasing)
  • road setting out and levels layout
  • road construction details (where different to our standard details)
  • road longitudinal sections
  • kerbing layout
  • drainage layout including Sustainable Drainage Systems (SuDS)
  • drainage construction details (where different to our standard details)
  • drainage longitudinal sections
  • finishes layout
  • vehicle swept path analysis (For residential areas, use the "Large Rigid Vehicle" as defined by the Freight Transport Association; for bus routes, use a 13.5m bus; for non-residential, use the longest likely vehicle.)
  • road adoption plan
  • land factoring plan
  • Quality Audit – including Road Safety Audits together with the Designer's Responses
  • signs and lines drawing
  • traffic signals layout and operational details
  • street lighting layout and calculations
  • vehicle charging points and connections
  • general arrangement and structural details for structures associated with the road network
  • any other details required to enable the assessment of the proposal

1.4.2 Supporting documents

East Lothian Council checksheets

You will find it helpful to complete the checksheets below before making a submission. These identify what we we will be looking for as we assess the Road Construction Consent.

Neighbour Notifications

The developer is required to notify any person who owns land which fronts, abuts or is comprehended in the new roads, or which lies within 50m of the road for which Road Construction Consent is being sought. You can use Form CC3 to issue the notifications.

Scottish Water Approval

Evidence of Scottish Water's Technical Approval will be required, and this must reference current revisions of the drawings.

Email flooding@eastlothian.gov.uk with any queries relating to drainage and flooding.

Drainage Assessment

Evidence that the Drainage Assessment, including a Surface Water Management Plan has been submitted to and approved by the Statutory Authorities.

Any questions about the Drainage Assessment requirements should be directed to flooding@eastlothian.gov.uk.

DNO comments on EV infrastructure

We require confirmation from the DNO (electrical Distribution Network Operator, currently SPEN for our area) regarding the suitability of the grid connection for vehicle chargers.

Questions should be directed to evcharging@eastlothian.gov.uk.

Structures Technical Approval

Where the submission includes structures associated with the road network (e.g. retaining walls, culverts or bridges) the application will be subject to Technical Approval Procedures as outlined in CG 300 of the Design Manual for Roads & Bridges, and Technical Approval must be sought before the application for an RCC. If the need for an additional or amended structure arises after the granting of Road Construction Consent, the developer should seek the approval of the Council’s Roads Authority before starting construction of it.

Any questions about Structures Technical Approval should be directed to bridges@eastlothian.gov.uk.

Lighting Calculations

Please note that you will be expected to ensure that lighting on existing roads is suitable for any new accesses. Email stlighting@eastlothian.gov.uk with any queries relating to lighting.

Mineral Working Report

In areas that are known to have been in-filled or have a history of mineral workings, we may require a mineral report together with supporting information on ground stability.

Note: These webpages are for reference by developers of housing and employment sites in East Lothian. They provide guidance on transport infrastructure against which Planning Applications will be assessed and evaluated, and set out East Lothian Council's procedures regarding the construction and adoption of new roads in accordance with current legislation. These pages supersede all previous versions of our Standards for Development Roads document. 

Revisions 

  • 01/07/2023 Document release
  • 03/07/2023 Added links to Bisaccount in S1.4.1 and minor updates to S1.4.2 Supporting Documents
  • 03/08/2023 Changed reference to charging for RCCs to omit start date
  • 06/10/2023 Added ELC checksheets to S1.4.2 Supporting Documents
  • 22/11/2023 Added clarification that affordable housing sites will be required to pay for an RCC
  • 29/01/2025 Added reference to forms CC1, CC2 and CC3 for use in the event that the portal is unavailable
  • 24/04/2026 Updated RCC processing fees
Road Construction Consent - Application Forms and Guidance
  • CC1 Application for Road Construction Consent PDF 79 KB
  • CC2 Docquets of Service PDF 90.92 KB
  • CC3 Notice of Service PDF 511.52 KB
  • CC5/N Application for Inspection DOTM 36.3 KB
  • CC6 Application for Adoption PDF 76.59 KB
  • Lighting - Forms of Completion and Inspection Certificate DOC 34 KB
  • Lighting - Installation Certificate DOC 28 KB
  • Lighting - Commissioning Test DOC 23.5 KB
  • Blank RCC form PDF 469.81 KB
  • RCC Checksheet - roads XLSX 217.67 KB
  • RCC Checksheet - lighting XLSX 23.92 KB
  • RCC checksheet - car charging XLSX 29.74 KB
  • RCC checksheet - structures XLSX 23.73 KB
  • RCC checksheet - travel plans XLSX 26.44 KB