The Construction Method Statement will include a section on Construction Traffic Management for plant and contractors' vehicles both on- and off-site, and will also include mitigation measures to control dust, noise and floodwater.
The documents should be constantly monitored and reviewed to account for changing circumstances.
Hours of construction work/business – care should be taken to avoid adding to congestion at peak times/school times:
Details of wheel-washing facilities including confirmation that these will be maintained in working order and will be used to prevent deleterious materials being carried onto the public road.
Details of how/when the surrounding roads and paths will be swept to keep clear of soil falling from loads.
Details of whether off-site parking for construction vehicles or contractors will be needed and where this will be accommodated.
Confirmation that pedestrian routes around the site will be remain accessible or suitable alternative arrangements made.
Site map showing:
Area map showing routes along East Lothian roads.
Details of how SuDS features (e.g. porous paving) and setted surfaces will be protected during the build.
Details of how surface water run-off will be controlled during the build.
Details of how contractors, visitors and suppliers will be informed of the existence of these policies, and how they will be enforced.
Where the construction traffic will significantly increase traffic on a local road, details of the dates of dilapidation (condition) surveys should be given, and a commitment made to restore these.
Where traffic is expected to be significantly different to the 'average' traffic on a road, swept paths should be shown for tight bends etc. and mitigating factors proposed.
Note: These webpages are for reference by developers of housing and employment sites in East Lothian. They provide guidance on transport infrastructure against which Planning Applications will be assessed and evaluated, and set out East Lothian Council's procedures regarding the construction and adoption of new roads in accordance with current legislation. These pages supersede all previous versions of our Standards for Development Roads document.
Revisions
01/07/2023 Document release
05/09/2023 Changes to definition of Construction Method Statement
12/09/2023 Changes to scope of Area Map, and addition of requirements regarding (1) dilapidation surveys and (2) swept paths